Aeration Systems
Architectural Products
Barrier: Highway
Basements: Precast, Thermal-Krete
Box Culverts
Bridge: 3 Sided Rigid Frame
Bridge: Arch-Parabolic
Bridge: Arch-Culvert
Bridge: Abutment System- Precast
Bridge: Steel Beam Precast Deck
Buildings
Catch Basins
Chlorine Tanks
Communication Manholes
Curbs: Precast Curb
D.O.T. Products - NEW YORK STATE DEP. OF. TRANS.
Distribution Boxes
Dosing Chambers
Electrical Catalog
Erosion: Cable Concrete
Grease Interceptors
Headwalls
Leaching Chambers
Lift Stations
Lifting Procedures
Light Bases
Manhole: Communication
Manhole: Sanitary/Storm
Manhole: Power
Manhole: Pump Stations
Meter/Valve Pits "Water"
Monuments & Markers
Oil Separators
Parking Bumpers
PermEntry
Pipe, Concrete End Section
Power Manholes
Pull Boxes
Pump Tanks
Retaining Walls: Kast-Block
Retaining Walls: Kast-Block Max
Retaining Walls: Evergreen
Retaining Walls: Redi-Rock
Roof Slabs
RPZ-Vaults & Buildings
Sanitary/Storm Manholes
Septic Tanks
Septic Tanks: Accessories
Septic Tanks: Traffic
Septic Tanks: Venting
Square/Rect. Structures - Vaults - Chambers
Stormwater Detention
Stormwater Treatment
Transformer Pads
Trench Drain
Tunnels: Precast
Used Equipment for Sale
Utility Structures
Water Meter Structures
Locations, Approvals, Certifications & Warranties
History, Mission, Vision, and Pledge
Mini Catalog
Project Pictures
Video Links
Erosion: Cable Concrete < prev  |  next >
03) Cable Concrete Installation
Click on a thumbnail to view larger photos
Description
Cable Concrete is an easily installed erosion control solution.

Here are the steps in a typical Cable Concrete installation:
*The slide show displays a picture for each of these steps.

1.) Grade and shape the area, removing any rock capable of puncturing the geotextile fabric. Cable Concrete is very flexible and will conform to the grade cut.
2.) Cable Concrete arrives via tractor trailer with a spreader bar to offload and place the mats. The weight per mat = product designation (CC: 20,35,45,70)* 64 sq. ft. per mat. The mats can be placed directly from the truck or stockpiled for later use. Care must be taken to avoid sudden jolts to the suspended mats.
3.) The mats are placed in their finale position with the center of each mat touching the surface first, always lay the project out to the center of each mat.
4.) Continued placement follows proceeding from the downstream end to the upstream end.
5.) Cables from adjoining mats are pulled together and a clamp loosely installed at the location show on the drawings. The clamp is pushed up the cables to provide tension on both cables and tightened. Minimal movement of the mats should occur after the clamps are installed and tightened.
6.) After the mats are clamped and anchored, the gaps between the blocks can be filled with the required material with a rubber tire loader (depending on block size, loader size, good judgment is called for). The material should be worked into the crevices using a shovel and broom as a finale step. The area can then be seeded and mulched as required or left to vegetate naturally.


Contact Us


< prev  |  next >
8713 Read Road • P.O. Box 218 • East Pembroke, NY 14056 • Tel. 585.762.8216 • Fax 585.762.8315